ejmoska - Wednesday, May 4, 2016 3:06 AM:
Hello,
At this time we have our R&D department which makes the initial specification with manufacturer parts. after approval and entry to production there are occasions when purchasing department find alternative , cheaper MPN's for our currently used parts. What is the mechanism to add AML parts to a released part?
Using ECR/ECN doesn't seem to do the job , any tips?
Thank you very much
eapu - Wednesday, May 11, 2016 12:34 AM:
Hello,
please see MCO, that's what you want.
? MCO – Manufacturing Change Order - used to edit an Approved Manufacturers List (the AML tab on Parts) after a Part has been released.
Lin
eapu - Wednesday, May 11, 2016 12:38 AM:
Hi,
Please see MCO.
MCO – Manufacturing Change Order - used to edit an Approved Manufacturers List (the AML tab on Parts) after a Part has been released.
Lin